Step-by-Step Action Plan for Dream Realization

In the planning of the airport development before 2030, all construction projects will be implemented in two stages and in two areas.

Development strategies and goals for major construction projects are divided into stages and areas.

zones

Existing Land

Acquired New Land

Development Phases

2016-2020

Zones-Existing Land

Ground Improvement

  • Airside Facilities Reinforcement

Facility Improvement

  • T1 BHS System Improvement
  • Yuanshan Apron Construction
  • Cargo Area Parking Lot

Terminal Construction

  • Terminal 3 Area Construction

Zones-Acquired New Land

Newly Expanded Land Planning


North Area Ground Leveling and Drainage; 3rd Runway and Satellite Concourse Planning and Environmental Impact Assessment (EIA)

Development Phases

2021-2030

Zones-Existing Land

Ground Improvement

  • Parallel Taxiway on The North Side of The North Runway
  • NP Taxiway Extension(West Side)

East Side Area of EC Taxiway Replanning

  • EC Taxiway Expansion (South Section)
  • Hangzhan S. Rd. Underpass
  • EC Taxiway Expansion (North Section)

Terminal Construction

  • Completion of Terminal 3

Zones-Acquired New Land

Newly Expanded Land Development


  • Develop the 3rd Runway, Satellite Concourse (West) (Including All Relevant Construction Work) and New Maintenance Area
  • Develop Free Trade Zone and New Cargo Area
*Phases are tentative due to the progress of new land acquisition